Darlington Unit 3 refurbishment moves to reassembly phase

DCN-JOC News Services
Darlington Unit 3 refurbishment moves to reassembly phase

TORONTO—Ontario Power Generation (OPG) has reported that its refurbishment of the Darlington plant’s Unit 3 is progressing well, with the project team moving into the stage of reassembling the unit.

The progress report came in OPG’s Q3 report, released Nov. 8.

“Leveraging lessons learned from the first unit refurbishment at Darlington, disassembly of Unit 3 was completed safely and with quality,” said Ken Hartwick, OPG president and CEO, in a statement. “This is thanks to the outstanding planning, collaboration and execution by the team while safely working under both COVID-19 restrictions and hot summer conditions.”

OPG also reported its financial and operating results for the third quarter of 2021, with net income attributable to the shareholder of $426 million, compared to $386 million for the same period last year.

As well, OPG recently announced its Reconciliation Action Plan. The firm has set a goal of increasing its existing economic impact for Indigenous communities and businesses to $1 billion over the next 10 years through ongoing operations, projects and initiatives. 

 