Acciona decries wastewater treatment plant contract cancellation

The Canadian Press
Acciona decries wastewater treatment plant contract cancellation
ACCIONA — Acciona Canada writes in a statement it has performed approximately $100 million in contracted work on a wastewater treatment plant in North Vancouver, B.C., for which it claims it has not received payment and adds contrary to Metro Vancouver officials work continues on the build. On Oct. 15 Metro Vancouver Regional District announced it had terminated its contract with Acciona.

VANCOUVER — A company formerly contracted to build a wastewater treatment plant in North Vancouver, B.C., calls the deal’s cancellation “regrettable, unnecessary,” and against the community’s interests.

The Metro Vancouver Regional District announced Oct. 15 it had terminated its contract with Acciona when the plant’s price tag rose from $500 million to $1 billion.

But Acciona says it’s done about $100 million in contracted work on the North Shore Wastewater Treatment Plant, for which it says it has yet to be paid.

The company says in a written statement that the project has been “fraught with unforeseen challenges” including “flaws in the design provided by Metro Vancouver as part of the original bid process.”

The company says its officials have been meeting with regional authorities over the past six months to negotiate a way forward, and it is “regrettable that Metro Vancouver has chosen to take this unnecessary and counterproductive course of action.”

The chief administrative officer for the regional district said the project was 36 per cent complete when by Acciona’s timeline it should be at 55 per cent.

It was intended to be completed by 2020.

Jerry Dobrovolny said it’s unusual to cut ties with a contractor, but the decision was made to shield taxpayers from further costs.

“This is a last resort, certainly not something we would have wanted to do or a position we would have wanted to be in. At some point we have to say enough is enough,” Dobrovolny said in an interview.

He said the regional district will now work to find a contractor on an expedited basis.

Acciona’s website says the company is also responsible for construction of the Broadway SkyTrain expansion as well as the Pattullo Bridge replacement.

 

© 2021 The Canadian Press