The accompanying tables show the top 10 major upcoming Oil & Gas and Electric Power & Communications construction projects in Canada. They are all in the planning stage and are mainly new projects, but may also involve additions and/or alterations.
Shopping centers, hotels, office buildings, medical buildings, educational buildings, government buildings, industrial projects, oil and gas projects, and electric power and telecommunications projects will all be covered on a rotating basis.
There are several reasons for highlighting upcoming large projects. Such jobs have often received a fair amount of media coverage. Therefore, people in the industry are on the lookout for when job-site work actually gets underway. And, as showcase projects, they highlight geographically where major construction projects are proceeding.
Finally, total construction activity is comprised of many small- and medium-sized projects and a limited number of large developments. But the largest projects, simply by their nature, can dramatically affect total dollar volumes. In other words, the timing and size of these projects have an exaggerated influence on market forecasts.
Project Title and Owner/Developer |
Location | Current Stage |
Project Value canadian $ |
---|---|---|---|
ELLS RIVER OIL SANDS FACILITY | |||
Chevron Canada Ltd | Fort Mackay AB | Pre-Design | $16,800,000,000 |
GOLDBORO LNG – LIQUEFIED NATURAL GAS EXPORT FACILITY | |||
Pieridae Energy – Halifax | Goldboro NS | Construction Documents | $10,000,000,000 |
ÉNERGIE SAGUENAY – LIQUEFIED NATURAL GAS COMPLEX | |||
GNL Québec Inc – Énergie Saguenay | La Baie QC | Pre-Design | $9,000,000,000 |
SINOCAN GLOBAL – BITUMEN UPGRADING AND PETROCHEMICAL FACILITY | |||
Teedrum Inc. | St Michael AB | Pre-Design | $8,500,000,000 |
NORTH WEST UPGRADER – STURGEON REFINERY PHASE 2 & 3 | |||
Canadian Natural Resources Ltd. (CNRL) | Fort Saskatchewan AB | Pre-Design | $8,500,000,000 |
WEST COAST OLEFINS ETHYLENE PRODUCTION PLANT | |||
West Coast Olefins Ltd. | McLeod Lake BC | Design Development | $5,600,000,000 |
PEMBINA (PDH/PP) FACILITY | |||
Pembina Pipeline Corporation | Sturgeon County AB | Construction Documents | $4,900,000,000 |
PIKE 1 IN-SITU PROJECT | |||
Canadian Natural Resources Ltd. (CNRL) | Chard AB | Construction Documents | $4,700,000,000 |
BEAR HEAD LNG PROJECT | |||
LNG Limited | Point Tupper NS | Design Development | $4,000,000,000 |
NAUTICOL ENERGY – METHANOL FACILITY | |||
Nauticol Energy Ltd. | Grand Prairie AB | Design Development | $3,200,000,000 |
Project Title and Owner/Developer |
Location | Current Stage |
Project Value CANADIAN $ |
---|---|---|---|
MACTAQUAC GENERATING STATION UPGRADES | |||
NB Power | Keswick Ridge NB | Pre-Design | $3,000,000,000 |
SUNDANCE 7 POWER PLANT | |||
TransAlta | Fallis AB | Construction Documents | $1,600,000,000 |
HACKNEY HILLS WIND PARK | |||
Aeolis Wind Power Corporation | Fort St John BC | Pre-Design | $1,000,000,000 |
THUNDER MOUNTAIN WIND ENERGY FACILITY | |||
Brookfield Renewable Partners | Tumbler Ridge BC | Pre-Design | $1,000,000,000 |
ONTARIO POWER GENERATION – DEEP GEOLOGIC REPOSITORY | |||
Ontario Power Generation Inc | Mar ON | Design Development | $1,000,000,000 |
SASKPOWER – GREAT PLAINS POWER STATION | |||
SaskPower | Moose Jaw SK | Design Development | $800,000,000 |
ATCO HEARTLAND GENERATING STATION | |||
Heartland Generation | Sherwood Park AB | Construction Documents | $800,000,000 |
FORTY MILE WIND POWER PROJECT | |||
RES Canada | Bow Island AB | Pre-Design | $650,000,000 |
TAZI TWÉ HYDROELECTRIC GENERATING STATION (ELIZABETH FALLS) | |||
Black Lake Denesuline Nation | Stony Rapids SK | Pre-Design | $360,000,000 |
SHARP HILLS WIND FARM | |||
EDP Renewables Canada Ltd. | Sedalia AB | Construction Documents | $510,000,000 |