Skip to Content
View site list

Profile

Pre-Bid Projects

Pre-Bid Projects

Click here to see Canada’s most comprehensive listing of projects in conceptual and planning stages

Infrastructure, Resource

Site C Check In: $10.7-billion hydro project moving ahead on schedule

Grant Cameron
Site C Check In: $10.7-billion hydro project moving ahead on schedule
BC HYDRO — Site preparation work continues at the massive Site C project. Seen here is a North bank excavation haul road in April. Other early works include building access roads and two temporary cofferdams across the main river channel to allow for construction of an earthfill dam.

After a tumultuous start, construction work on the 1,100-megawatt Site C hydroelectric dam and generating station on the Peace River in northern British Columbia is moving ahead as planned and the project remains on budget, says Dave Conway of BC Hydro, community relations manager for the $10.7-billion venture.

The sprawling site where the massive dam is being built is a beehive of activity, with more than 2,300 workers — mostly from B.C. — doing site preparation and excavation work, and building access roads and two temporary cofferdams across the main river channel to allow for construction of an earthfill dam.

“Contractors for various project components are continuing construction and operations in their work areas,” said Conway.

“This includes the main civil works, generating station and spillways civil works, turbines and generators, and substation. Construction activities such as drilling, blasting, crushing, earth moving, pile driving, steel-pile installation, concrete placement and road maintenance are continuing.”

Allteck Line Contractors Inc. is expected to start preliminary work soon for building two new 500-kilovolt, 75-kilometre transmission lines along a right-of-way between the Site C project and the Peace Canyon generating station. The lines will deliver power generated at the dam to the rest of B.C.

An Aecon, Flatiron, Dragados, EBC Partnership is doing the spillways civil works component of the project, which includes placement of 700,000 cubic metres, or the equivalent of 280 Olympic-sized swimming pools, of reinforced concrete and 34,000 tonnes of rebar. The partnership signed a $1.6-billion contract in the spring.

Geotechnical investigations and survey work are also being done for realignment of segments of Highway 29. Contracts for the highway work are yet to be awarded.

When completed, there will be an earthfill dam about 1,050 metres long, a generating station with six 183-megawatt generating units, and an 83-kilometre-long reservoir that will be three times the width of the river.

 

According to BC Hydro, construction work on the $10.7-billion, 1,100-megawatt Site C hydroelectric dam and generating station on the Peace River in northern British Columbia is moving ahead as planned. Pictured is in-river work taking place in April.
BC HYDRO — According to BC Hydro, construction work on the $10.7-billion, 1,100-megawatt Site C hydroelectric dam and generating station on the Peace River in northern British Columbia is moving ahead as planned. Pictured is in-river work taking place in April.

 

Conway said that, as of the end of March, about $2.4 billion had been spent on the project and BC Hydro has contracts and agreements in place totalling nearly $6 billion. The project budget was raised to $10.7 billion in January. It was initially lower but was revised upwards due to cost overruns.

Site C has been a controversial project. The provincial NDP government had promised a review of the project as part of its election platform. A review was conducted and, last December, the NDP decided to proceed.

Then, in mid-February, clearing and road access work along a section of the Site C transmission line corridor was stopped after West Moberly First Nations filed a civil case, alleging its rights were being violated.

Conway said that, following that request, BC Hydro stopped clearing and access road work at the west end of the transmission line until Oct. 1 or when a court decision on an injunction is made.

While stakeholders in the B.C. construction industry are glad the project is going ahead, as it’s providing jobs for the sector, they are worried about a shortage of skilled trades as the project ramps up.

 

More than 2,300 workers are currently carrying out site preparation and excavation work at the Site C dam project. Pictured is North bank shotcrete placement above the Inlet portal in April. As of the end of March, about $2.4 billion had been spent on the project and BC Hydro has contracts and agreements in place totalling nearly $6 billion.
BC HYDRO — More than 2,300 workers are currently carrying out site preparation and excavation work at the Site C dam project. Pictured is North bank shotcrete placement above the Inlet portal in April. As of the end of March, about $2.4 billion had been spent on the project and BC Hydro has contracts and agreements in place totalling nearly $6 billion.

 

Chris Atchison, president of the B.C. Construction Association (BCCA), said there’s a construction boom going on across the country and the focus is to ensure the contractors get the workers they need.

“It’s not any different there than elsewhere in B.C. where there’s work,” he said. “It’s a challenge that construction employers are having all across the province and at Site C it’s no different.”

Atchison said the BCCA is trying to make sure that workers are aware of the opportunities that exist at Site C.

“In the early stages there are enough, but as they ramp up they’re going to need more and that’s going to continue to put pressure on the workforce in the province.”

Darrel Reid, vice-president of policy and advocacy at the Progressive Contractors Association of Canada (PCA), said finding trades might be difficult down the road, especially if a $40-billion LNG facility goes ahead on B.C.’s coast.

“A lot of people are expecting to see the LNG project move ahead in the next year and if that’s the case then we are going to be short of workers,” he said.

PCA and other associations are working to expand the trades workforce, but with all the provinces going full tilt it’s difficult to get workers to come to B.C., said Reid.

“We’re going to need a lot of workers in the next decade so there’s no sugar-coating that. A whole bunch of very smart people are working on ways to try to get more young people and women and First Nations into the trades. But it’s no doubt there is going to be a scramble for qualified workers.”

Tom Sigurdson, executive director of the B.C. Building Trades Council, said the challenges facing contractors on Site C are because of the labour model used earlier in the project by B.C. Hydro.

“It’s no secret that the Building Trades has been a vehement voice against the open shop labour supply model used at Site C and we believe it’s the main reason there have been so many challenges providing opportunities for local residents, apprentices, women in trades and Indigenous workers,” he said. “While some of those concerns remain, we are eager to move forward and pleased to see more of our workers on the site, building a legacy project that will provide clean power for many decades.”

 

Recent Comments (1 comments)

comments for this post are closed

Darryl R Taylor Image Darryl R Taylor

This article highlights a frustration that I personally have with both those who benefit from the continuation of the site C project, and those opposed to it:

No one has done a fleshed out analysis of what the costs and employment numbers would be for placing a more decentralized and diversified power generation network equivalent in total production ( or exceeding) the Site C dam.

Aside from sparing a stretch of alluvial lowlands that likely serves as the ecological biodiversity reserve for each of the regions that the Peace River passes through on it’s way through the Peace Athabasca Delta and on up to the Mackenzie in the NWT, there are a host of benefits to decentralized power generation.

The addition of site C to BC’s inventory of power production would place better than 45% of our production capacity upon a single watercourse. There are a multitude of things that can go wrong with that situation, both naturally occurring disasters and those caused by human action.

The same weakness also lies in the transmission bottleneck.

In a province overdue for a megatheust earthquake, at a time when the climate is undergoing notable alterations, altering the hydtogeologic systems of two provinces and a territory rather than hsving localized power ptoduction(when possible) seems imprudent.

With localized power generation and a flexible sustem of transmission with redundancy of routing options, regardless of any disaster or circumstancethe greatest number of people would continue to have power continuity, and thus be in then best position to help those whose generation or distribution capacity was impacted.

The construction process would creatajust as many or more jobs as the megadam, while allowing greater access to that work for peoplewithfamilies and roots in their communities.

Regional pride is also something worthy of consideration, along with the fact thatby having generation sources nearer to the end users, their functional awareness collectively of the source of their power would ne more concrete.

That latter point is not inconsiderable in it’s import, in ordertomeet ouroreven approximste our carbon emissions targets for the mid-century without finding much more power thsn Site C would add to ourdupply, we need to make conservation of energy a second nature, instinctive value for our population.

Without hard numbers, such alternatives remain firmly stuck in the world of the imagination, limiting our options to a dam whose need has been attributed to factors that have shifted even more than it’s budget or the clay “bedrock” that it is supposed to rest on.

The Clean Energy Act of 2010 was a de facto tailroading of this ptoject, the environmental reviews used the dame filigent “creative accounting” that BC Hydro has become famous for, and the energy from it will be no more “clean” than Albertan “ethical oil”.

Where are the options with substance?

More

You might also like