Certificate of Completion
Form ID
Publication date
Location of premises
Municipality of Red Lake
Golden Ward Water Treatment Project Hwy. 125, Cochenour, Ontario
Golden Ward Water Treatment Project Hwy. 125, Cochenour, Ontario
Certificate
Cochenour Water Treatment Plant, Balmertown Reservoir/Pumping Station, 6 km Feeder Main, Low Lift Station Modifications and other miscellaneous works as set out in the contract drawings and specifications prepared by Keewatin-Aski Ltd., dated July 2003
- Date substantially performed:
- Date certificate signed:
Participants
- Name of Owner
- The Corporation of the Municipality of Red Lake
- Address of Owner
- PO Box 1000, Balmertown, ON P0V 1L0
- Name of Contractor
- Parkwest Projects Ltd.
- Address of Contractor
- Box 52, Grp 525, RR 5, 1077 Oxford St. W., Winnipeg, Manitob
- Name of Certifier
- Keewatin-Aski Ltd., Consulting Engineers
- Address of Certifier
- PO Box 510, Sioux Lookout ON P8T 1A8
Office to which claim for lien must be given to preserve lien
Keewatin-Aski Ltd., PO Box 510, Sioux Lookout ON P8T 1A8