- Various Locations: Rodney, Port Glasgow, New Glasgow, Tyrconnell, Duttona
- This is to certify that the contract for the following improvement:
- Substantial Completion of Project ELG_09_NFTC to construct and implement high-speed broadband services in Elgin County
- To the above premises was substantially performed on:
- August 16, 2023
- Date certificate signed:
- December 7, 2023
- Name of owner:
- Southwestern Integrated Fibre Technology Inc.
- Address for service:
- 789 Broadway St., Wyoming ON, N0N 1T0
- Name of contractor:
- North Frontenac Telephone Corporation Limited
- Address for service:
- 5405 Eglinton Ave W, Suite 214, Toronto ON, M9C 5K6
- Office to which claim for lien must be given to preserve lien:
- Executive Director, Southwestern Integrated Fibre Technology Inc. 789 Broadway St, Wyoming ON, N0N 1T0