Skip to Content
View site list

Profile

Pre-Bid Projects

Pre-Bid Projects

Click here to see Canada’s most comprehensive listing of projects in conceptual and planning stages

Government

Legal Notes: Running the risk of exaggerated lien claims

John Bleasby
Legal Notes: Running the risk of exaggerated lien claims

Lien claims that are exaggerated well beyond what is actually owed for work done or made without supporting evidence run the risk of being reduced in amount or even thrown out entirely.

Two recent appeals in British Columbia provide insights that might offer guidance in other jurisdictions.

In the first, a contractor providing drywall, insulation and steel studwork on a multi-storey commercial project claimed to be underpaid as per the contract. It was also claimed that the project owner had interfered with work, causing added expense. The contractor filed a lien for $1,136,000, far beyond the $575,576 owed for the work completed. The owner paid security on the full amount but filed a counterclaim saying the contractor’s lien was grossly inflated and an abuse of process.

“The trial judge awarded the contractor $575,576 for the work it performed on the project, but dismissed the Interference Claim, which represented the balance of the total Lien value,” writes Dan Melnick, associate with Clark Wilson Law LLP.

However, the justice did not feel there was an abuse of process, despite false information provided by the contractor’s project manager regarding the alleged interference by the owner. Therefore, the owner was denied any damages resulting from the financing cost incurred by posting the full security amount.

The British Columbia Court of Appeal (BCCA) overturned this decision.

“The contractor abused the mechanisms of the act to secure funds it knew or ought to have known it was not entitled to, and in doing so caused the owner to suffer damages: the time value of the money held in court as security for the portion of the lien relating to the interference claim,” writes Melnick.

Accordingly, the contractor was ordered to pay damages equal to that portion of the interest on the security related to the interference claim, from the date the security was paid until the date of the trial judgment.

The owner learned a lesson as well as the contractor. Since the owner did not produce evidence regarding the actual interest cost incurred, the interest cost damages were calculated under B.C.’s Court Order Enforcement Act, an amount lower than what was likely paid by the owner.

A second case involved a lien claim that was exaggerated in the extreme.

Thomson LLP partners Emma Johnston and Cobi Dayan, and summer student Annie Redmond, describe how Darwin Construction (BC) Ltd. filed a lien against PC Urban Glenaire Holdings Ltd. for $3 million.

An initial contract had been awarded to Darwin for $14,758,947. Approved change orders brought the total to $15,958,282. By the time the contract was terminated, Darwin had invoiced the partnership for $15,619,761 and been paid a total of $14,004,124, including the portions of the holdback.

“The developer (PC Urban Glenaire) applied to have the lien cancelled in its entirety, or to have the amount of the security for the lien reduced to a nominal amount of $1,” write Johnston, Dayan and Redmond.

The chambers judge ruled the $3 million claim was clearly excessive and reduced the security paid against the lien by PC Urban Glenaire to $500,000.

In a ruling described as “a first decision of its kind,” the BCCA cancelled the lien entirely, due to the inflated amount of the claim and other clear abuses of process.

Although it doesn’t happen often, Johnston, Dayan and Redmond note that provinces have their own lien acts and other statutes that allow their courts to remove or cancel improper liens, or award costs and damages due to exaggerated or falsely claimed liens.

The appeals court acknowledged, “there are times that in the haste to secure a lien claim after termination of a contract, a lien claimant might miscalculate the lien.”

However, it added that, “the lien claimant has to be prepared to support an arguable case as to both the right to the lien and the amount of the lien.”

John Bleasby is a Coldwater, Ont.-based freelance writer. Send comments and Legal Notes column ideas to editor@dailycommercialnews.com.

Recent Comments

comments for this post are closed

You might also like