OPG says Darlington on schedule and on budget

The Canadian Press
OPG says Darlington on schedule and on budget

TORONTO—Ontario Power Generation (OPG) says its multibillion-dollar Darlington refurbishment is on time and on budget one year into the project.

The crown corporation says in its quarterly results that about $4.1 billion of the $12.8 billion budgeted for the project had been spent as of Sept. 30. The power generator’s net income came in at $140 million for the third quarter, down from $198 million in the same quarter last year.

The company says the decrease was due to the Darlington units being taken off-line and because its application to the Ontario Energy Board for an adjusted rate has not yet been approved. OPG says revenues were $1.2 billion in the third quarter, down from $1.4 billion in the same quarter last year for the same reasons.

The company’s total power generation for the quarter was 19.4 terawatt hours, compared with 19.5 terawatt hours for the same quarter last year due to the lower generation at Darlington, partially offset by its Pickering operation.