Open house being held for Welland Thorold powerline project

DCN-JOC News Services
Open house being held for Welland Thorold powerline project

WELLAND, ONT. — On Tuesday, Nov. 19, Hydro One will be hosting an open house to share details about the Welland Thorold powerline project in an effort to gather feedback from Indigenous communities, elected officials, property owners, businesses, residents and other interest groups.

Stretching approximately 18 kilometres from the Crowland Transformer Station in Welland to an existing transmission line in Thorold, the proposed project is expected to add 400 megawatts of capacity to the grid, explains a release.

The open house will be held at the Royal Canadia Legion at 383 Morningstar Ave. in Welland from 2 to 7 p.m.

 

Welland Thorold powerline project map

 

The project is being proposed because electricity demands in Niagara Region are expected to increase by approximately 20 per cent between now and 2032. Ontario’s Independent Electricity System Operator has recommended the new transmission line come into service no later than 2029. 

For more information about the project and to learn about the preferred route selection process, visit HydroOne.com/WTPL.

To provide feedback or to be added to the contact list contact Hydro One at: 1-877-345-6799 or Community.Relations@HydroOne.com